Extra/Stakeholder information.docx

And here's a list of the personnel involved in the project:

These 2 were in my original project charter:

         General manager and project sponsor (Beth Smith)

         Assistant manager and project manager (Kaitlin Greene)

         Sales associates (random list of names):

o   Jane Montgomery

o   Lisa Johnson

o   David Robertson

o   Ashley Brown

o   Brian Ford

For the stakeholders, let's go with: (From text, Pg. 342-343) Project Sponsor Project Team Project manager Employees Shareholders Customers Suppliers and contractors Government agencies (Code compliance permits etc.)

Extra/W2WBS_Greene.docx

Reference

Project Management Institute, Inc. (PMI) (2013). A Guide to the Project Management Body of Knowledge (PMBOK Guide) (5th ed.). p. 66. Global Standard: Newtown Square, Pennsylvania.

Restucturing Plan for Hallmark Card & Gift Shop

[0]

Staff

[1]

Project Management

[2]

Introduction of updated terminals

[4]

New store layout

[3]

Project sponsor will monitor project

[1.1]

Project manager will be the main staff member to execute project

[1.2]

Five additional staff members will assist in restructuring

[1.3]

Same staff must be involved in each store opening

[1.4]

Each staff member be assigned individual tasks

[1.5]

Detailed project charter

[2.1]

Create and follow budget

[2.2]

Train staff

[2.3]

Oversee each step of reconstruction

[2.4]

Ensure quality at each stage

[2.5]

Construction plan

[3.1]

Find and buy materials

[3.2]

Follow reorganization plans

[3.3]

Assign construction tasks

[3.4]

End store layout meets expectations

[3.5]

Compare and contrast terminals

[4.1]

Determine what the terminal needs for success

[4.2]

Buy terminal

[4.3]

Install terminal

[4.4]

Learn to operate and use in daily operations

[4.5]

Complete Project

[5]

Follow project charter

[5.1]

Stay within budget

[5.2]

Ensure quality at each stage

[5.3]

Execute project

[5.4]

Project is completed, stores open for business

[5.5]

Extra/WBS.mpp

BYP 13-7 is located in the Broadening Your Perspective section at the end of Chapter 13 in the WileyPLUS Readings.   

 

After you have reviewed the facts presented in BYP 13-7, what is your assessment of the ratios listed for 2013 and 2014?  In other words, do the calculated ratios present a favorable picture?  Are these ratios relevant to the loan officer's lending decision?

 

What is at least one other ratio (not posted by another student) that the loan officer would want to calculate for this company?  Include an explanation as to why you selected the ratio.

 

 

Please read INSTRUCTORS instructions carefully and completely

Due date 4/23/15 in 4 hours

No plagiarism in own words

Will run through a plagiarism checker

Will not accept if after due date will dispute

References page must include a valid URL to take the reader to the electronic copy of each source.

If cannot complete with the given instructions do not reply

Please contact me if you have questions

Write as a discussion with another student

Make a question out of the response, or I found the material interesting, or what do you think

I may ask to change some areas at later date

100 to 200 word count

Word count is counted by answer only

Please write with question first followed by answer

Please write clearly simplify

I am in the U.S.

No charts or graphs

Project/(READ to understand topic) Risk Management Plan.docx

Risk Management Plan 1

Introduction

This plan documents and communicates the processes, tools, and procedures that will be used to manage and control risk events that could have a negative or positive impact on the Hallmark Store Restructuring Project and the project’s stakeholders. It is the governing document for managing and controlling any and all project risks.

Purpose of the Risk Management Plan

· To identify as many risk events as possible prior to the commencement of the project

· To remain alert to the development of any new events during the project life cycle that may impact the project and therefore require identification

· To analyze, assess and classify all risks in order to minimize their impact

· To maximize the opportunities available for the project’s stakeholders, schedule, and products

· To develop controls, monitoring systems and documented mitigation plans to manage the identified risks

· To develop appropriate responses to, and contingency plans for, those risk events that do materialize

· To provide contingency funds to cover risk events that actually materializes.

Methodology Statement

A risk is defined as any uncertain event or condition that, if it occurs, could either prevent the project from progressing as planned, or could interfere with its successful completion. Some risks, hereinafter referred to as opportunities, have a positive impact on the project, and in order to leverage the full benefit of these opportunities, early identification is preferred. Risks can be identified from a number of different sources, and some are more readily identifiable than others. This risk management strategy will attempt to identify all such readily identifiable risks prior to the commencement of the project. There are some risks, however, that may not become readily apparent until a later stage during the project cycle, and should they occur, they may be identified or detected at their onset by anyone who is connected to the project. There are also some risks that are inherent based on the nature of the project, while others may arise as a result of external influences that are outside of the control of the project team. The Hallmark Store Restructuring Team Project Manager has the overall responsibility for managing project risk, and project team members will be assigned specific areas of responsibility for reporting to the Project Manager. Risk management will be performed at all levels of the project in order to ensure adequate coverage of all potential problem areas (AcqNotes, 2015).

Risk Management Process

· Risk Identification

· Risk Assessment

· Risk Response Development

· Contingency Planning

· Opportunity Management

· Contingency Funding and Time Buffers

· Risk Response Control

· Change Control Management

Risk Response Matrix

Risk Event

Response

Contingency Plan

Trigger

Who Is Responsible

Exceed Budget

Mitigate: Get funds

Contingency funds will be set aside prior to the start of the project to cover any risk events that actually materialize.

Immediately after request for more funds

Manager and Finance Department

Decrease in Sales

Mitigate: Monitor competitors

Offer discounts for one week to boost sales

Advertise more, see what the competitors are doing

Marketing and Sales Department

Product/Fixture Damage

Mitigate: Replacement

Transfer: Warranty

Replace with a new one immediately

Order replacement

Manufacturing Department

Technical problems with new terminals

Mitigate: Use old version

Use old terminals and slowly change to the new one plus offer training

Not solved within 24hrs

Manufacturing Department and IT Department

Final store layout does not meet quality standards

Mitigate: reconstruction

Order for the reconstruction

Not solved within 1 month

Manager

Risk Identification

Risk identification consists of determining which risks are likely to affect the project and documenting the characteristics of each. This component of the risk management process shall remain a significant topic of discussion throughout all phases of this restructuring project to maintain project team commitment to risk awareness, identification, documentation and communication. Risk awareness requires project team members to remain cognizant at all times of what constitutes a risk to the project, and to develop a sensitivity to specific events or factors that could potentially impact the project in a positive or negative way. Risk communication involves bringing risk factors or events to the immediate attention of the Project Manager and project team. Open communication is an essential part of this risk management strategy as it is required in order to provide all project personnel with the freedom to identify issues without negative consequences to themselves. Joint management of risks between Hallmark store owners, management, vendors, and contractors, along with full support from the project team and all employee stakeholders is also necessary to enable identification of the most important risks to the project and to support efficient allocation of mitigation resources (AcqNotes, 2015).

Known and potential risk factors will first be identified and documented utilizing a Risk Breakdown Structure Diagram (RBS) (phe.gov). It is the Hallmark Store Restructuring Team Project Manager’s responsibility to assist the project team and other stakeholders with risk identification, and to document all known and potential risks on the RBS. Updates to the RBS will occur throughout the project life cycle as risk factors change. Risk management will be discussed regularly during weekly scheduled project meetings or sooner, if the situation warrants. During these meetings, the Hallmark Store Restructuring project team will discuss any new risk factors or events, and these will be further reviewed with the Project Manager (phe.gov). The Project Manager will then determine if any of the newly identified risk factors require additional evaluation. Those that do will undergo risk quantification and risk response development, as appropriate (phe.gov). Any risk factors or events discovered at any time during the project must be brought to the attention of the Project Manager via Email or other form of written communication in order to properly document the item (phe.gov). The Project Manager is responsible for logging the risk, if appropriate, to the RBS. Once additional risks are identified and noted, the Project Manager will then begin the risk assessment and risk response procedures to properly neutralize or mitigate the risk.

The Risk Breakdown Structure, shown below, has revealed several probable risks for further analysis.

Risk Breakdown Structure (RBS)

After discussing all the probable risks, the project team has decided that five of these risks are serious, and should be assessed further. These risks are described below.

· Risk #1: Exceed Budget

· The projects set budget may be exceeded and the owner would be required to take money from the emergency contingency funds. Unexpected costs could include more labor to be paid if the project exceeds the timeline, contractors needing to be hired if the store’s staff is unable to complete technical or physical tasks, or more materials are needed for the project than expected.

· Risk #2: Decrease in Sales

· During the renovation, customers may feel inconvenienced if certain gift or card sections of the store that they want to shop in are under construction. They may leave the store and bring their business elsewhere.

· Risk #3: Product/Fixture Damage

· During the restructuring of the store, products that are for sale may become damaged or physical parts of the store may be damaged. Moving large objects throughout the store could be cumbersome and knock holes in the walls or damage shelves or displays. When repainting the walls, paint could spill on the carpets requiring a carpet cleaning service.

· Risk #4: Technical problems with new terminals

· The new register terminals will be installed by the terminal company’s technicians. This is part of the project that our staff will have no control over. There may be problems with the stores wiring, internet connection, or there may not be enough room for the terminals or technical equipment. The technicians may also initially install the terminals incorrectly and service calls may be needed. The staff may also have a difficult time adjusting to the new system.

· Risk #5: Final store layout does not meet quality standards

· The final store layout may not live up to the expectations that the project manager had. The new layout could possibly be even more confusing to the customers. Or the quality of the construction may be below expectations. The vision for the reconstruction of the store may not come to fruition.

Risk Assessment

Capital planning is a methodology of recognizing, examining and selecting venture to focus on association's consumptions on resources whose money streams are required to augment past one year. It's an essential procedure in light of the fact that capital uses oblige huge venture yet constrained by the accessibility of stores (Capital Rationing), incredibly impacts a company's capacity to attain to its budgetary targets, and can get to be as a device of control (Chance & Brooks, 2015). 

Instabilities can exist when the result of an occasion is not known for certain, and when managing resources whose money streams are required to expand past one year, unquestionably, there's component of risk in that circumstance. The assessment of risk in this way depends on leader capacity to distinguish and comprehend the way of vulnerability encompassing the key variables and on the other, having the instruments and system to process its risk ramifications. Different dependable guidelines are regularly used. (Chance & Brooks, 2015). 

An estimation of the extent to which a firm or task acquires a blend of settled and variable expenses.

1. A business that makes couple of offers, with every deal giving a high gross edge, is said to be profoundly utilized. A business that makes numerous deals, with every deal contributing an exceptionally slight edge, is said to be less utilized. As the volume of offers in a business builds, every new deal contributes less to settled expenses and more to productivity.

2. A business that has a higher extent of altered expenses and a lower extent of variable expenses is said to have utilized all the more working influence. Those organizations with lower settled expenses and higher variable expenses are said to utilize less working influence.

The higher the level of working influence, the more prominent the potential risk from estimating risk. That is, if a generally little mistake is made in gauging deals, it can be amplified into vast lapses in income projections. The inverse is valid for organizations that are less utilized. A business that offers a large number of products a year, with every contributing marginally to paying for altered expenses, is not as subject to every individual deal.

Although these viewpoints are essential, it merits accentuating the part of risk, particularly product risk, since this may help as a guiding instrument. It may help to discover the harmony between 'building the correct thing', 'constructing the thing right', and 'building it quick'.

Numerous activities don't have boundless time, cash and assets for assessing the nature of the product. Such limitations as far as time, cash and assets speak to requirements on the outcome to be accomplished and hence frequently diminished assessment conceivable outcomes of the product chances. Accordingly, it is essential to attain to a decently considered harmony between the interest in cash and time from one perspective, and the outcomes to be attained to and the risks secured on the other. The aftereffect of the product risk examination gives the avocation to this equalization.

In view of the knowledge coming about because of the product risk investigation, high risk events can be assessed more seriously than those speaking to a lower risk. Be mindful that risks and how to cover these risks are straightforwardly related to the acknowledgement criteria. These acknowledgement criteria are accessible in different structures.

There are numerous methodologies on the most proficient method to focus risks. However as a rule one could say: These methodologies include dissecting the product to be assessed with the point of attaining to a joint perspective - for and with all partners - of (the properties of) the product to be assessed that speak to higher and lower risk levels, such that relating measures can be relegated to this perspective.

General undertaking business dangers are imparted by most organizations yet their centrality shifts by organization. On account of new businesses or early stage organizations, administration must pick up involvement in overseeing operational, promoting and different issues that will emerge. Potential dangers incorporate surprising issues that may grow in quality control, dispersion, showcasing and advancement and different zones. (Pritchard & PMP, 2014). New companies and early stage organizations should likewise manufacture associations with clients and draw in clients from contenders. Little yet settled organizations have effectively picked up experience managing these issues, diminishing this business risk. The danger investigation area ought to specify these risks and vulnerabilities, and the strategy for success segments identifying with every danger class ought to have systems to manage them. (Chance & Brooks, 2015). 

Although all organizations face vulnerabilities connected with the general monetary environment, a few ventures are less business cycle delicate than others. The monetary cycle danger of a nourishment organization, for instance, may be to a lesser degree a worry than is the situation of a development organization. Banks are presented to premium rate risks yet numerous have set up systems to relieve those vulnerabilities. A few organizations are presented to difficulties postured by higher fuel costs, while real estate agents are presented to dangers identifying with lower home deals. The critical thing is to distinguish which of these general business difficulties could affect the business and have methodologies to manage them. Organizations ought to have methods to balance out their business and keep on succeeding notwithstanding unforeseen changes in the monetary environment. (Ayyub, 2014). 

The business confronts perils connected with characteristic fiascos. These identify with changes of the climate and their results, for example, time lost underway and dissemination and resultant monetary downturns that discourage deals. On account of organizations that offer restrictive items, there are instabilities connected with responsibility for property. It is imperative to have trademarked brand name and patent security to forestall replication of organization items or administrations, which could have an unfriendly impact on the organization and influence the result of protected innovation rights question. (Davies, 2014). 

Qualitative and Quantitative Risk Analysis

Definitions of Probability

Probability of Occurrence

Equivalent Probability Score

Very High

> 0.9

Greater than 90%

5

High

0.7 -0.899

Between 70-90%

4

Medium

0.3 – 0.699

Between 30-70%

3

Low

0.15 – 0.299

Between 15-30%

2

Very Low

< 0.15

Lower than 15%

1

Risk Assessment Form

Risk Event

Likelihood

(Probability Score)

Impact

Detection Difficulty

When

Exceed Budget

3

4

1

Installation

Decrease in Sales

4

5

1

Start-up through

Installation

Product/Fixture Damage

3

3

3

Installation

Technical Problems

2

4

4

Installation

Store Quality Standards not met

1

5

4

Post-Installation

To Calculate Risk Value: Impact * Probability * Detection

Risk Severity Matrix

5

4

Likelihood

Decrease in Sales

3

Product Fixture Damage

Exceed Budget

2

Technical Problems

1

Store Quality Standards Not Met

1

2

3

4

5

Impact

Red Zone (Major Risk)

Yellow Zone (Moderate Risk)

Green Zone (Minor Risk)

Risk Value Calculation

Risk Value

Exceed Budget: (3 x 4 x 1)

12

Decrease in Sales: (4 x 5 x 1)

21

Product/Fixture Damage: (3 x 3 x 3)

27

Technical Problems: (2 x 4 x 4)

32

Store Quality Standards not met: (1 x 5 x 4)

20

To Calculate Risk Value: Impact * Probability * Detection

Risk Response Development

Risk Response Development is the next step after risks have been identified and assessed. In this phase the Project Manager will begin the process of deciding which response is most appropriate for each given event (Larson & Gray, p. 214, 2014). In some cases, the decision may be made to mitigate, or reduce the impact or likelihood of the risk by using various proven strategies and tools. In other cases, it may be more practical to avoid the risk altogether by altering the project’s plan in some way. There is also the possibility that a risk may be either too large or too remote to either mitigate or avoid it completely; in cases such as these the Project Manager may opt to retain or accept the risk (Larson & Gray, p. 216, 2014).

2.4.1 Risk Monitoring, Controlling, and Reporting

Following and observing the recognized risks, distinguishing new risks, executing risk reaction plans, and assessing their viability all through the task life cycle. The procedure of risk administration can be grounded on an unmistakable seeing about the nature and extent of choice making inclusion in task administration and a characteristic structure for looking at these choices is the venture life cycle. For fruitful usage of the undertaking, a consistent checking strategy of risk is basically needed in all the sections of this structure like conceptualization, arranging, configuration, development, end and transfer of a task. (Pritchard, & PMP, 2014). Risk Monitoring and Control is the procedure of recognizing, dissecting, and making arrangements for recently emerging risks, staying informed concerning the recognized risks and those on the watch rundown, reanalyzing existing risks, observing trigger conditions for alternate course of actions, checking remaining risks, and auditing the execution of risk reactions while assessing their adequacy. The Risk Monitoring and Control process applies strategies, for example, change and pattern examination, which oblige the utilization of execution information created amid undertaking execution. Risk Monitoring and Control, and in addition the other risk administration methods, is a progressing procedure for the life of the venture. (Davies, 2014). 

These aforementioned techniques can be viably clarified by utilizing a contextual analysis. The contextual investigation clarifies the ordinary risks that a real development venture is constantly presented to and through this contextual investigation the creator needs to demonstrate that regardless of the possibility that the administration group has done a detailed examination of risks, they can never say that they have recognized all the risks in light of the fact that still there are chances for a few risks being forgotten as unidentified. (Davies, 2014). 

A detailed data about the danger at individual advance level and at portfolio level are obliged to deal with the credit chance viably. It is additionally the assignment of danger reporting, an autonomous unit of the business division, to combine and procedure the data identified with danger controlling and to total it into a danger report covering the accompanying four regions:

· The report needs to demonstrate the improvement of the aggregate portfolio and sub-portfolios regarding danger; besides, critical individual positions must be expounded on.

· The report must cultivate the requirement for activity that is fundamentally hazard alleviation measures, coming about because of the appraisal of future business sector inclines, the coordination with danger bearing limit and danger methodology, and additionally discoveries from dissecting the opposition

· The danger report needs to clarify how the measures will influence the foundation's danger circumstance and what the due date for the usage of the measures is.

· The danger report must outline the effectiveness of danger distinguishing proof, appraisal and control, by uncovering frail/hazardous focuses to be handled later on and a fleeting rule for concerns to be under the inner review consideration.

The danger division/area readies the danger report and submits it to the danger council. The report's level of subtle element must be adjusted to the data needed by the beneficiary for every situation. This would require an examination as to the needs of the separate choice making levels, bringing about the readiness of reports as per those needs. In its last form, the credit danger report ought to contain all levels of point of interest to guarantee that the information imparted inside the bank are reliably accessible for all levels of subtle element ought to those information be needed in the choice making methodology. (Davies, 2014). 

It is imperative that the business and budgetary dangers be distinguished and talked about in the undertaking strategy for success. The educated reader, particularly one who may be approached to give money to the business, needs to be agreeable that the administration has considered potential dangers and created methods to manage them. During the time spent adding to the marketable strategy, ID of potential dangers won't just result in a superior arrangement additionally better plan administration to effectively deal with the undertaking. Readers will have a less positive perspective of a composed undertaking arrangement that does exclude a danger investigation area than one that exhibits that administration is mindful of vulnerabilities and is arranged to take activities to address any risk.

Risk Response Matrix

Risk Event

Response

Contingency Plan

Trigger

Who Is Responsible

Exceed Budget

Mitigate: Get funds

Contingency funds will be set aside prior to the start of the project to cover any risk events that actually materialize.

Immediately after request for more funds

Manager and Finance Department

Decrease in Sales

Mitigate: Monitor competitors

Offer discounts for one week to boost sales

Advertise more, see what the competitors are doing

Marketing and Sales Department

Product/Fixture Damage

Mitigate: Replacement

Transfer: Warranty

Replace with a new one immediately

Order replacement

Manufacturing Department

Technical problems with new terminals

Mitigate: Use old version

Use old terminals and slowly change to the new one plus offer training

Not solved within 24hrs

Manufacturing Department and IT Department

Final store layout does not meet quality standards

Mitigate: reconstruction

Order for the reconstruction

Not solved within 1 month

Manager

Contingency Planning

Contingency Planning is necessary to create an alternate course of action if a predicted risk event materializes. The plans formulated under this heading will only be enacted in the event that a risk is recognized. These alternatives will be detailed in the Risk Response Matrix section of this risk management plan.

Opportunity Management:

The Opportunity Management section of the risk management plan addresses events that could have a positive effect on the project. Once these risk events are identified and assessed, the Project Manager will then make a decision on whether to exploit, share, enhance or accept these opportunities.

Potential positive risks of this project would be:

· Completing the project in less time than expected

· Completing the project under budget

Contingency Funding and Time Buffers:

The Contingency Funding and Time Buffers section of the risk management plan addresses monetary and time “cushions” that will be put in place on this project in order to cover project risks associated with costs and scheduling. These funds are independent of the original time and cost estimates, and will only be activated if a budget overage or project delay related risk materializes (Larson & Gray, p. 223, 2014).

· Time Buffer

· The current project timeline is as follows:

Store

Timeline

Store #1

2 ½ weeks

Store #2

1 ½ weeks

Store #3

1 week

Store #4

1 week

Store #5

1 week

· Additional time up to two weeks will be allotted in case there are setbacks in the project.

· Contingency Funding

· Total budget for all five store’s restructuring is $32,200 (Includes cost of staff labor, new terminals, and construction materials)

· Contingency funds on reserve will be $2,000 with the potential need of requesting a bank loan

Risk Response Control

The Risk Response Control section of the risk management plan is contained within the Risk Register, which is the cornerstone of the risk control process. During this process, we will execute our risk response strategy, which will include “monitoring triggering events, initiating contingency plans, and watching for new risks” (Larson & Gray, p.224, 2014).

2.9 Change Control Management

Change Control Management is the final phase in the risk management plan. In this section we will establish a change review and control process for dealing with any required project changes, and we will define the formal, acceptable method of communication and decision making that will be employed to evaluate and accept or reject changes (Larson & Gray, p.226, 2014).

Change Control Process Flow diagram

Change Request Submitted to Project Manager

Change Request Reviewed by Project Manager

Approved

Project Plan is updated to reflect Changes

Revised Plan is distributed to project team and stakeholders

Yes

No

Change Originates

All project changes must first be submitted to the Project Manager on a Project Change Request Form for review. In the event that authorization is also required from other project stakeholders, the Project Manager will first sign off on the change request, and will then submit it to the relevant parties for additional review and authorization. The Project Manager is responsible for determining the impact of any and all approved changes on the project. Each requested change must be also be noted in the Change Request Log, as this will ensure that a complete history of all change requests is always accessible for review. Once the Change request is approved, the project plan is updated by the designated member of the project team, and copies of the amended project plan are distributed to members of the project team and to all stakeholders.

3. Conclusion

After completing this risk management plan, the project manager will now be thoroughly prepared for potential risks and issues pertaining to this store restructuring plan. Through visual representations such as the risk assessment form and risk severity matrix, the top five potential risks have been identified and given a response. Each risk event has been given an educated numerical score based on its likelihood, impact, detection difficulty, and when the risk would be able to be evident. Each risk event has also been shown how it would affect the projects costs, time and schedule, scope, and quality. Overall, the project at hand has a high chance for success now that the project manager has identified potential risks and has resolution plans in place if any of these risks materialize.

References

AcqNotes (2015) Risk & Safety Management: Generic Plan for Project Risk Management. Retrieved from: http://acqnotes.com/acqnote/tasks/risk-management-plan

Ayyub, B. M. (2014). Risk analysis in engineering and economics. CRC Press.

CDC (2015). “Project Risk Management Plan Template”. Retrieved from: http://www2.cdc.gov/cdcup/library/templates/CDC_UP_Risk_Management_Plan_Template.doc

Chance, D., & Brooks, R. (2015). Introduction to derivatives and risk management. Cengage Learning.

Davies, J. C. (2014). Comparing environmental risks: tools for setting government priorities. Routledge.

Larson, E. W., & Gray, C. F. (2014). Project Management, The Managerial Process (6th ed.). p. 222-226. New York: McGraw Hill.

O'Riordan, T. (Ed.). (2014). Environmental science for environmental management. Routledge.

PHE (Public Health Emergency) (July 2013). Risk Management Documents. U.S. Department of Health & Human Services. Retrieved from: http://phe.gov/about/amcg/toolkit/Pages/default.aspx

Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.

Project Management Body of Knowledge, PMBOK 5th edition. (2013). Project Risk Management. p. 309-349. Newtown Square: Project Management Institute.

Project/(You can read) Time, cost, and procurement.docx

3). Time

Store

Timeline

Store #1

2 ½ weeks

Store #2

1 ½ weeks

Store #3

1 week

Store #4

1 week

Store #5

1 week

This project will begin with a restructuring of the biggest storefront that owner and General Manager Beth Smith has in Tampa. The project will respectively continue with restructuring the remaining four locations that she owns throughout Hillsborough County and Pinellas County. Project Timeline

Project start date: March 23rd, 2015

Projected finish date: May 4th, 2015

Projected project duration: 7 weeks

* Store #1 is the biggest storefront of the owner’s franchise so this location will take slightly longer to restructure than the other stores since it is larger.

*Store #2 will also take slightly longer because the employees will still adjusting to what the best methods are for restructuring. This extra ½ of a week will also provide extra time to overcome any potential obstacles.

4). Cost

Resource Requirements & Budget

· Staff hourly labor ($8.00/hour)

· There will be 5 staff members dedicated to the project that will be responsible for each store’s restructuring. The project is estimated to take 7 weeks to complete and approximately 35 hours a week from each staff member will be dedicated to the project. Not included in the calculation is the salary of the general manager and the assistant manager as they will not be the main staff physically dedicated to executing the project.

· Total estimated labor cost: $9,800 (5 staff members * 35 hours per week * 7weeks * $8.00/hour)

· New signage (20 new signs for each store)

· Estimated cost per sign: $20

· Total estimated sign cost: $400

· New terminals (2 for each store, 3 for the biggest storefront)

· Estimated cost per terminal: $2,000 each

· Total estimated terminal cost: $22,000 (11 terminals @ $2,000 each)

· Total budget for all 5 store’s restructuring: $32, 200

Cost Management

Responsible for managing costs:

Project Manager- Kaitlin Greene

Has authority to make budget changes and approve additional purchases/ costs:

Project Sponsor- Beth Smith

Project Manager- Kaitlin Greene

Cost status:

Project Manager will perform a budget evaluation and create a progress report to review with the Project Sponsor twice a week

8). Procurement

Project Supply Chain Issues and Procurement Strategy for Hallmark Store Restructuring Plan

Introduction

The objective of the following is to identify project needs and determine how project needs will be efficiently met. The store restructuring plan for Hallmark needs a procurement strategy and an identified supply chain structure. The supply chain consists of partners that provide materials and assistance needed to complete the project. It also takes into account the financial considerations and selection criteria involved in procuring outsourced help (Korn, 2013).

Purpose

The purpose of a procurement strategy is to identify and establish project needs that will be met by acquiring products and services from outside sources. After this is done, the plan then conducts the process of choosing a supply chain partner(s) and establishing contracts. The following diagram outlines the stages involved in the procurement process.

Procurement Data Flow Diagram

Project Needs

Project needs must be first identified to know all products needed for the project and what type of suppliers must be procured to fulfill these product needs. For this project, construction materials for all five store renovations will include new store signage, organizational shelving, and new register terminals.

The register terminals are the priority to procure as they will have the biggest impact on the store restructuring plan and they will cost the most. For the biggest store, 3 terminals will be needed. For the remaining 4 stores, 2 terminals each will be needed. A total of 11 terminals will be needed.

Fixed-price contract

A Firm Fixed Price Contracts (FFM) is the most suitable contract option for this project because the construction materials and the number of new terminals have already been predetermined and can be easily specified in the contract. The price of materials are not subject to change unless the scope of the work (defined by the project manager) changes.

Make-or-Buy-Analysis

The project team consisting of Hallmark assistant manager and 5 sales associates will be completing all but one project assignment. The project team (paid a standard hourly minimum wage rate) will be responsible for reconfiguring the store layout, installing new shelving system, and hanging all new signage. These tasks will only require outsourced help if the team is physically not able to complete the tasks.

Project assignments that will require outsourced contracting will be the installation and setup of the new register terminals and the purchases of shelving and signage materials. An IT company that sells the terminals and a construction material company will be procured based on the following selection criteria:

· Quality of references that the seller can provide

· Whether the prices of their products and installation services align with our budget

· Level of technical expertise

· Guarantee of needed delivery dates

Conduct Procurements

This stage will include evaluating various sellers’ bids and offers. The main proposals that we will focus on will be from terminal register suppliers. We will then evaluate and rank sellers based on the previously defined selection criteria.

The next step will be to select sellers that will be qualified to perform the work and who meet our criteria. Contracts will then be awarded, preferably a Firm Fixed Price Contract with each seller.

Control Procurements

Actively controlling project procurements is the next important stage. This will consist of managing procurement relationships, predicting risks and overcoming obstacles. We will avoid risks by controlling the quality of project tasks at each stage.

Concerning each contract with each seller, we will monitor contract performance by ensuring the seller upholds their agreements. Changes or corrections will be made to contracts as needed.

Close Procurements

This final stage is to conclude the project while updating records to reflect final results.

Conclusion

Project management will follow this plan to procure a supply chain network to complete project tasks. It is recommended to drive the project team in a cross-functional manner to optimize what they can do without outside contracted help (Atkinson, 2005). It will be more cost effective to have the project team complete as many tasks on their own as possible. It is unavoidable to spend money to procure construction materials, new terminals, and the expertise of IT professionals to install the terminals though.

References:

Atkinson, W. (Sep. 2005). "Project management strategies for procurement: organizing and driving cross-functional teams stacked with a new set of skills." Purchasing: 17+. Academic OneFile. Retrieved from: http://db24.linccweb.org/login?url=http://go.galegroup.com/ps/i.do?id=GALE%7CA136206962&v=2.1&u=lincclin_spjc&it=r&p=AONE&sw=w&asid=c01f6aa65bd5ec7bf849f22abd4e5b24

Korn, M. (2013, Jun 05). The hot new M.B.A.: Supply-chain management; more schools are ramping up their programs, adding majors and concentrations as employer demand grows. Wall Street Journal (Online) Retrieved from: http://search.proquest.com/docview/1364887242?accountid=36653

Project Management Body of Knowledge, PMBOK (2013). A Guide to the Project Management Body of Knowledge. (5th ed.). (pg. 355-370). Newtown Square: Project Management Institute.

Sample Project Management Plan. Retrieved from: http://innovativeprojectguide.com/sample-project-plans/14-sample-plans/161-sample-project-management-plan-pmp.html

1). Project Start-up

2). Risk management plan

3). Identify project needs

6). Contract preparation

5). Supplier market assessment

4). Create a procurement strategy

7).Bidding process/ negotiations

8).Supplier Selection

9). Finalize contracts

10). Product delivery

11). Control Procurements

12). Implementation

13). Project closure/ update records

Project/Group Instructions.docx

Instructions

Week 6 – Project Management Plan – Team Assignment - 45 points

All Team Members Complete Together, Submit Individually to the Drop box

Based on their risk assessments, groups will prepare a project management plan for their selected project. The group will choose an appropriate framework for the project plan, select the needed components/sections and assign them for completion to specific team members. The team will include the team charter addressing the specific tasks assigned to team members (remember to include the team charter within the project plan). The project management plan should address specific controls resulting from the risk assessment, as well as measurement and communications requirements for the progress of the project. The project management plan will be as comprehensive as possible, with specific notation of sections and items which will be further developed as the project progresses.

1. A written project management plan will be provided including all needed materials (all elements, please review PMBOK pg 76+).

2. The team will also provide a short briefing covering  their project management plan.

Hint:

A. Submit a MS Word Doc - Use and include all knowledge management elements in PMBOK for the Project Management Plan. The project management plan must contain the 10 knowledge management areas: Integration (the Project Management Plan Overview), Scope, Time, Cost, Quality, Communication, Human Resources, Procurement, Risk, Stakeholder. You should identify what and how you plan to handle each element in a 1-2 page narrative. You should use tables or graphics also to substantiate.

B. Include the Team Charter, Risk Management Plan, Project Charter, and WBS you already developed in the appropriate sections of the Project Management Plan. You will want to ensure your paper describes each area as is appropriate for the Project Management Plan and then if you wish attach to appendix the original charter, etc. You must ensure your plan specifically identifies the knowledge area and how it relates to your project even if you attach the original document. Do not simply write "see appendix xx". Do not assume the team charter, WBS, etc. completely fulfills the Project Management Plan for HR, Time, etc.

C. Submit a second MS Word Doc - Ensure you include a separate presentation which should cover all areas of the project management plan. You may record a video (~10 minutes) or create a PowerPoint presentation, etc.

Project/More/Team 3-WBS created on Schedule Pro.docx

1- Hallmark

Restructuring

Plan

1.1- Staff

1.1.1- Project sponsor

monitors project

1.1.2- Project manager

leads execution

1.1.3- Select five staff

members needed

for restructuring

team

1.1.4- Team must

continually assist

in each store's

reconstruction

1.1.5- Assign each

member unique

tasks

1.2- Project

Management

1.2.1- Create detailed

project charter

1.2.2- Create budget

1.2.3- Train staff

1.2.4- Oversee and

critique each

stage of

reconstruction

1.2.5- Ensure quality at

each stage

1.3- New Store

Layout

1.3.1- Receive and

review

construction plan

1.3.2- Find and buy

materials

1.3.3- Follow

reorganization

plans

1.3.4- Assign

construction tasks

1.3.5- End store layout

meets expectations

1.4- Updated

Terminal

Introduction

1.4.1- Determine what

features terminal

must have

1.4.2- Compare/contrast

terminal options

1.4.3- But terminal

1.4.4- Install terminals

1.4.5- Learn to operate

and train

accordingly

1.5- Complete All 5

Store

Reconstructions

1.5.1- Follow project

charter

1.5.2- Stay within

budget

1.5.3- Ensure quality at

each stage

1.5.4- Execute projects

1.5.5- Project

completion, open

stores for business

1

- Hallmark

Restructuring

Plan

1.1

- Staff

1.1.1

- Project sponsor

monitors project

1.1.2

- Project manager

leads execution

1.1.3

- Select five staff

members needed

for restructuring

team

1.1.4

- Team must

continually assist

in each store's

reconstruction

1.1.5

- Assign each

member unique

tasks

1.2

- Project

Management

1.2.1

- Create detailed

project charter

1.2.2

- Create budget

1.2.3

- Train staff

1.2.4

- Oversee and

critique each

stage of

reconstruction

1.2.5

- Ensure quality at

each stage

1.3

- New Store

Layout

1.3.1

- Receive and

review

construction plan

1.3.2

- Find and buy

materials

1.3.3

- Follow

reorganization

plans

1.3.4

- Assign

construction tasks

1.3.5

- End store layout

meets expectations

1.4

- Updated

Terminal

Introduction

1.4.1

- Determine what

features terminal

must have

1.4.2

- Compare/contrast

terminal options

1.4.3

- But terminal

1.4.4

- Install terminals

1.4.5

- Learn to operate

and train

accordingly

1.5

- Complete All 5

Store

Reconstructions

1.5.1

- Follow project

charter

1.5.2

- Stay within

budget

1.5.3

- Ensure quality at

each stage

1.5.4

- Execute projects

1.5.5

- Project

completion, open

stores for business

1- Hallmark

Restructuring

Plan

1.1- Staff

1.1.1- Project sponsor

monitors project

1.1.2- Project manager

leads execution

1.1.3- Select five staff

members needed

for restructuring

team

1.1.4- Team must

continually assist

in each store's

reconstruction

1.1.5- Assign each

member unique

tasks

1.2- Project

Management

1.2.1- Create detailed

project charter

1.2.2- Create budget

1.2.3- Train staff

1.2.4- Oversee and

critique each

stage of

reconstruction

1.2.5- Ensure quality at

each stage

1.3- New Store

Layout

1.3.1- Receive and

review

construction plan

1.3.2- Find and buy

materials

1.3.3- Follow

reorganization

plans

1.3.4- Assign

construction tasks

1.3.5- End store layout

meets expectations

1.4- Updated

Terminal

Introduction

1.4.1- Determine what

features terminal

must have

1.4.2- Compare/contrast

terminal options

1.4.3- But terminal

1.4.4- Install terminals

1.4.5- Learn to operate

and train

accordingly

1.5- Complete All 5

Store

Reconstructions

1.5.1- Follow project

charter

1.5.2- Stay within

budget

1.5.3- Ensure quality at

each stage

1.5.4- Execute projects

1.5.5- Project

completion, open

stores for business

Project/More/Team 3-WBS Drawing.mpp

Project/More/Team 3-WBS Drawing.vsdx

Restructuring Plan 1 Staff 1.1 Project Sponsor Monitors Project 1.1.1 PM leads execution 1.1.2 Select 5 Members for Restructuring Team 1.1.3 Team assists with all stores 1.1.4 Tasks assigned to team members 1.1.5 Project Management 1.2 Create Detailed Project Charter 1.2.1 Create budget 1.2.2 Train staff 1.2.3 Oversee & critique reconstruction 1.2.4 New Store Layout 1.3 Receive & Review Construction Plans 1.3.1 Find & Buy Materials 1.3.2 Follow Reorganization Plans 1.3.3 Assign Construction Tasks 1.3.4 End- Store Layout Meets Expectations 1.3.5 Determine Terminal features 1.4.1 Terminal options 1.4.2 But terminal 1.4.3 Install terminals 1.4.4 Learn to operate & Train Accordingly 1.4.5 Reconstruction on all Stores Complete 1.5 Follow Project Charter 1.5.1 Stay within budget 1.5.2 Ensure Quality at Each Stage 1.5.3 Execute projects 1.5.4 Project End- Stores Reopen for Business 1.5.5 Ensure quality at each stage 1.2.5 Updated Terminal Introduction 1.4

Project/More/Week 6 -Team Powerpoint Template.pptx

Team 3: Charmaine Henriques, Kaitlin Greene, Daniel Faherty

Store Restructuring

Project Management Plan Overview

MAN 4583

April 26th, 2015

Project/Part 1- (READ to understand topic) Integration Management.docx

Integration Management Plan

Integration Management Plan

The Hallmark Card & Gift Shop Store Restructuring Project is being undertaken as part of a plan to optimize the total customer shopping experience, thereby subsequently boosting sales. The project will result in the creation of a more efficient store layout that will increase the ease and speed with which customers are able to locate merchandise, while simultaneously improving team member productivity through the installation of new checkout terminals.

In order to ensure smooth execution of this venture, we recognize that an effective project integration approach must be employed. With this in mind, we have established an Integration Management Plan that will provide a consistent, cohesive process for initiating, planning, executing, controlling, and closing the project (NV H.I.E., 2012). Adoption of this plan further requires our commitment to the following objectives:

1. The adaptation, maintenance and execution of all project plans and processes during project startup (NV H.I.E., 2012)

2. The establishment, and clear communication and maintenance of the project’s overall organizational structure (NV H.I.E., 2012)

3. The involvement, where appropriate, of all relevant internal and external project stakeholders in the definition, maintenance, and execution of the project’s management processes (NV H.I.E., 2012)

4. The establishment and maintenance of the project’s technical and administrative environment (NV H.I.E., 2012)

5. The integration and coordination of all associated project plans and processes (NV H.I.E., 2012)

6. The execution of closure activities for all the project’s plans and processes during project shutdown (NV H.I.E., 2012)

Project Integration Approach

· Scope Definition and Management:

The project scope statement will define the precise parameters of the project, while the Scope Management Plan will explain the method and specific tasks that will be utilized during the process of executing and managing those parameters throughout the duration of the project. This area of focus also covers the change management process.

· Time and Time Management:

The project work schedule identifies the key tasks, activities, timelines, and resources that have been defined for the execution of this project. The Schedule Management Plan details the methodology for managing, executing and controlling the project schedule to ensure timely completion of the project (PMI, 2013).

· Costs and Cost Management:

The project estimates and budget describe the total anticipated project expenditure, while the Cost Management Plan explains the project team’s approach towards planning, financing, managing and controlling project costs to ensure that the project is completed within the agreed upon budget (PMI, 2013).

· Quality and Quality Management:

The quality segment focuses on a discussion of cost-benefit analysis, quality standards and deliverables and overall quality expectations (PMI, 2013). The Quality Management Plan identifies the project team’s methodology for ensuring that the project’s end result meets Hallmark store’s quality standards, and satisfies all other identified project goals.

· Communications Management:

The Communications Management Plan identifies the methods and processes that will be utilized to ensure the efficient creation, dissemination, retrieval, storage, management, controlling and monitoring of all project information (PMI, 2013).

· Human Resources Management:

The Human Resources Management Plan will discuss the project team members and their respective roles, as well as the overall approach towards organizing, managing, and leading the project team throughout the duration of the project.

· Procurement Management:

The Procurement Management Plan describes the chosen methodology for managing and controlling the purchasing or acquisition of all products and services required for project completion.

· Risk and Risk Management:

The Risk Assessment Form and Risk Breakdown Structure explain the identified project risks, while the Risk Response Matrix and the Risk Management Plan discuss the project team’s

approach towards planning, monitoring, controlling and mitigating risk throughout the duration of this project.

· Stakeholder Management:

The project’s stakeholders will be identified, and the Stakeholder Management Plan will further describe the processes that the team will engage in to communicate with and engage stakeholders in project decisions and activities (PMI, 2013).

Integration

M

anagement

Plan

Integration Management Plan

Project/YOUR INSTRUCTIONS (this is what needs to be done).docx

You are responsible for the following:

(Each section requires 1 Page, including charts and diagrams)

Please also refer to the Professor's Week 6 instructions and Rubric to be sure you have everything that is required....

1. Quality Management Plan —Format Needs Research, Pg.231> in PMBOK is vague but may be a start

2. Human Resources Management Plan (Format- Pg.264 PMBOK and attached document)

3. Stakeholder Management Plan (PMBOK Pg. 406) and information posted in the learning material for week six. (More research may be needed to find a format and charts)

As you create the three sections above, if you follow the Integration Management Plan that I emailed yesterday, it will serve as a guide and will also help to keep the overall project cohesive, as the Integration plan is really an overview of all the sections that follow.

In addition to the above, you are also responsible for creating overview/summary PowerPoint slides for each of these 3 sections. (No more than 1-2 slides per section, you should have the PowerPoint format in one of the last emails I sent...

(These slides will take the place of an Executive Summary)

Get help from top-rated tutors in any subject.

Efficiently complete your homework and academic assignments by getting help from the experts at homeworkarchive.com