Path
Expected Duration
(weeks)
Variance
A
10                
1.21
B
8                
2.00
C
12                
1.00
D
15                
2.89
E
14                
1.44
The new director of special events at a large university has decided to completely revamp graduation ceremonies. Toward that end, a PERT chart of the major activities has been developed. The chart has five paths with expected completion times and variances as shown in the table. Graduation day is 16 weeks from now.
 
Assuming the project begins now, what is the probability that the project will be completed before:

(Round your z-value to 2 decimal places and all intermediate probabilities to 4 decimal places. Round your final answers to 4 decimal places.)
 
a.
Graduation time?
 
  Probability for graduation time
 
[removed]  
 
b.
The end of week 15?
 
  Probability at the end of week 15
[removed]  
 
c.
The end of week 13?
 
  Probability at the end of week 13
[removed]  
 

Get help from top-rated tutors in any subject.

Efficiently complete your homework and academic assignments by getting help from the experts at homeworkarchive.com