12.
Use the assignment method to obtain a plan that will minimize the processing costs in the following table under these conditions: |
|
|
WORKER |
||||
|
|
A |
B |
C |
D |
E |
|
1 |
14 |
18 |
20 |
17 |
18 |
|
2 |
14 |
15 |
19 |
16 |
17 |
Job |
3 |
12 |
16 |
15 |
14 |
17 |
|
4 |
11 |
13 |
14 |
12 |
14 |
|
5 |
10 |
16 |
15 |
14 |
13 |
|
a. |
The combination 2-D is undesirable. |
The sequence is . |
b. |
The combinations 1-A and 2-D are undesirable. |
The sequence is . |
13.
The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival. |
Job |
Processing Time (Days) |
Due Date (Days) |
Remaining Number of Operations |
A |
8 |
20 |
2 |
B |
10 |
18 |
4 |
C |
5 |
25 |
5 |
D |
11 |
17 |
3 |
E |
9 |
35 |
4 |
|
a. |
Determine the processing sequence at the first work center using each of these rules: (1) First come, first served, (2) Slack per operation. |
|
|
Sequence for First come, first served |
|
Sequence for Slack per operation |
|
|
b. |
Compute the effectiveness of each rule using each of these measures: (1) average completion time, (2) average number of jobs at the work center. (Round your answers to 2 decimal places.) |
|
First Come, First Served |
Slack per Operation |
Average completion time |
|
|
Average number of jobs |
|
|
|
14.
The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B. |
|
TIME (hours) |
|
Job |
Machine A |
Machine B |
a |
16 |
5 |
b |
3 |
13 |
c |
9 |
6 |
d |
8 |
7 |
e |
2 |
14 |
f |
12 |
4 |
g |
18 |
14 |
h |
20 |
11 |
|
a. |
Determine a sequence that will minimize makespan time. |
The sequence is . |
b. |
Find machine B’s idle time. |
Idle time |
hrs |
c. |
For the sequence determined in part a, how much would machine B's idle time be reduced by splitting the last two jobs in half? |
New idle time hrs, savings of hrs. |
16.
For each of the following network diagrams, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times. |
a. |
Activity-on-arrow diagram |
|
The critical path is . |
The expected project duration is . |
|
b. |
Activity-on-node diagram |
|
The critical path is . |
The expected project duration is . |
|
c. |
Activity-on-arrow diagram |
|
The critical path is . |
The expected project duration is . |
|
|
Top of Form
17.
For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project. |
a. |
Activity-on-arrow diagram |
Summary: |
|
|
|
|
|
Activity |
ES |
EF |
LF |
LS |
Slack |
1–2 |
|
|
|
|
|
2–4 |
|
|
|
|
|
4–7 |
|
|
|
|
|
7–10 |
|
|
|
|
|
10–12 |
|
|
|
|
|
2–5 |
|
|
|
|
|
5–8 |
|
|
|
|
|
8–10 |
|
|
|
|
|
1–3 |
|
|
|
|
|
3–6 |
|
|
|
|
|
6–9 |
|
|
|
|
|
9–11 |
|
|
|
|
|
11–12 |
|
|
|
|
|
|
b. |
Activity-on-node diagram |
Summary: |
|
|
|
|
|
Activity |
ES |
EF |
LF |
LS |
Slack |
1 |
|
|
|
|
|
2 |
|
|
|
|
|
3 |
|
|
|
|
|
4 |
|
|
|
|
|
5 |
|
|
|
|
|
6 |
|
|
|
|
|
7 |
|
|
|
|
|
8 |
|
|
|
|
|
9 |
|
|
|
|
|
|
c.
Activity |
Immediate Predecessor |
Estimated Time (days) |
A |
— |
15 |
B |
A |
12 |
C |
B |
6 |
D |
B |
5 |
E |
C |
3 |
F |
— |
8 |
G |
F |
8 |
H |
F |
9 |
I |
G |
7 |
J |
H |
14 |
K |
J |
6 |
End |
D, E, I, K |
|
|
Summary: |
|
|
|
|
|
Activity |
ES |
EF |
LF |
LS |
Slack |
A |
|
|
|
|
|
B |
|
|
|
|
|
C |
|
|
|
|
|
E |
|
|
|
|
|
D |
|
|
|
|
|
F |
|
|
|
|
|
G |
|
|
|
|
|
I |
|
|
|
|
|
H |
|
|
|
|
|
J |
|
|
|
|
|
K |
|
|
|
|
|
|
rev: 05_06_2014_QC_48798
Hints
the question score
eBooks & Resources
the assignment attempt score
Check my work
Check my work
Minimum score:
GO
student assignment preview
The student preview allows you to see your assignment screens as your students will see them.
Changes and selections you make while in student view (including clicking "submit assignment") will not be saved or otherwise affect any of your (or your students') settings, so feel free to explore!
save & exit in student assignment preview
This button has been disabled for instructors viewing the student assignment preview.
A student clicking this button would have any work done on this page saved and then be returned to the home page/assignment list.
Required Information
Ask your instructor a question
untitled
Enter your question.
/3000
Remember: You're responsible for submitting your assignment on time even if your instructor doesn't respond.
cancelsend
Top of Form
18.
Reconsider the network diagram. Suppose that after 12 weeks, activities 1-2, 1-3, and 2-4 have been finished; activity 2-5 is 75 percent finished; and activity 3-6 is half finished. How many weeks after the original start time should the project be finished? |
Project can be completed in a total of weeks. |
References
eBook & Resources
PROBLEM 2:
Problem 2-6
A manager checked production records and found that a worker produced 180 units while working 40 hours. In the previous week, the same worker produced 123 units while working 30 hours. |
a. |
Compute Current period productivity and Previous period productivity. (Round your answers to 2 decimal places.) |
|
|
|
Current period productivity |
|
Units / hr |
Previous period productivity |
|
Units / hr |
|
b. |
Did the worker's productivity increase, decrease, or remain the same? (Round your intermediate calculations and final answer to 2 decimal places. Omit the "%" sign in your response.) |
Worker's productivity by % |
2-7
b. |
Suppose a new, more standardized procedure is to be introduced that will enable each employee to process one additional customer per day. Compute the expected labor and multifactor productivity rates for each unit. (Round your "Labor Productivity" answers to 1 decimal place and "Multifactor Productivity" answers to 4 decimal places.) |
Unit |
Labor Productivity (customers per day per worker) |
Multifactor Productivity (customers per dollar input) |
A |
|
|
B |
|
|
C |
|
|
D |
|
|
|
Use α=.5 and β=.1, and TAF of 250 for period 5. Obtain forecasts for periods 6 through 10. (Round your intermediate calculations and final answers to 2 decimal places.) |
t Period |
TAFt |
6 |
|
7 |
|
8 |
|
9 |
|
10 |
|
|
311
A manager of a store that sells and installs spas wants to prepare a forecast for January, February, and March of next year. Her forecasts are a combination of trend and seasonality. She uses the following equation to estimate the trend component of monthly demand: Ft = 100 + 2t, where t = 0 in June of last year. Seasonal relatives are 1.13 for January, 1.07 for February, and .92 for March. What demands should she predict? (Round your answers to 2 decimal places.) |
Month |
Forecast |
January of the next year |
|
February of the next year |
|
March of the next year |
|
|
HELLO WORLD!
(Click to select)
-2-2
http://ezto.mhedu
(Click to select)
(Click to select)
undefined
17182580_12646
13252704044088
john.horne@my
John Horne
formerSID
13252704044088
f5f09e048269e00
-2-2
http://ezto.mhedu
-2-2
http://ezto.mhedu
-2-2
(Click to select)
x
x
http://ezto.mhedu
x
x
x
x
(Click to select)
-2-2
http://ezto.mhedu
(Click to select)
-2-2
(Click to select)
(Click to select)
-2-2
http://ezto.mhedu
http://ezto.mhedu
(Click to select)

Get help from top-rated tutors in any subject.
Efficiently complete your homework and academic assignments by getting help from the experts at homeworkarchive.com